Power Supply Restored In Karachi Through Joint Efforts Of KE And NTDC Teams
Karachi – May 22, 2021: KE’s 220 kV Extra High Tension network on Saturday afternoon experienced tripping along with the 220 kV NKI-Baldia 1&2 circuit. NTDC and KE teams immediately responded by coordinating closely for the restoration of the circuits. The connection with National Grid and subsequently power supply to all affected grids was restored […]
Power Supply In The City Normalized In Record 4 Hours After Gusty Winds And Dust Storm – K-electric
Karachi – May 18, 2021: Power supply in the city was brought to the routine levels in record time of almost 4 hours despite gusting winds and a severe dust storm, which hit the metropolis on Tuesday afternoon. K-Electric’s rapid response teams maintained strict vigilance as the city experienced strong winds along with light rain […]
KE Extends Eid Greetings, Remains Committed to Facilitate Customers
Karachi, 11 May 2021: Extending Eid wishes to consumers across Karachi and adjoining areas, KE announced that it would remain committed to providing maximum facilitation to customers during the three days of Eid ul Fitr. “On this auspicious occasion we wish all consumers a happy, safe, and blessed Eid. Alhamdulillah with the support of the […]
K-Electric partners with largest delivery platform foodpanda & leading tax filing portal Befiler
Alliance aims at promoting use of KE Live mobile app by offering exclusive discount on foodpanda App & Befiler Karachi – May 10, 2021: K-Electric has announced an exciting offer for new users of its KE Live Mobile application through strategic alliances with foodpanda – Pakistan’s largest delivery platform, and Befiler – the country’s leading […]
K-Electric Facilitates Customers by Extending Due Date of Bills
Karachi, 07 May, 2021: In order to facilitate the customers during Eid holidays K-Electric has extended the deadline for payments of electricity bills. This extension is applicable on bills with due dates falling between 10th May to 11th May,2021 both days included. These bills can now be paid latest by the new date of 20th […]
Governor Sindh visits K-Electric’s BQPS-III Power Plant, reviews Swift Progress of Unit One
Karachi: Governor Sindh Imran Ismail visited K-Electric’s Bin Qasim Power Station-III (BQPS-III) project to review the progress on the latest addition to Karachi’s power network. The visit followed a meeting between KE’s Senior Leadership and the Governor Sindh where KE presented an update on the company’s preparedness for Ramadan and the 2021 summer season. BQPS-III […]
K-Electric announces 9-Month Results; NEPRA Approval Critical for Continuity of Investment
Karachi, April 29th, 2021: K-Electric (KE) Limited’s Board of Directors approved the Company’s financial results for the 9-month period ended March 31,2021 at a meeting held on April 28, 2021 at KE Head Office. The Board of Directors were pleased to report a net profit of PKR 9.443 billion for the period under review, and an […]
K-Electric, Government of Sindh, ink MoU to Automate New Connection Process
Karachi, April 20, 2021: With a vision to facilitate customers and streamline the process of acquiring new connections under the World Bank’s Ease of Doing Business Index, K-Electric and Department of Energy Government of Sindh signed a Memorandum of Understanding (MoU) to automate the issuance of wiring test certificates for new connections. K-Electric has […]
KE plantation drive for 100,000 mangroves at BQPS – III
Karachi – April 14, 2021: As part of the environmental and social implementation programme for BQPS – III, KE celebrated the successful planting of 100,000 mangroves and launched a drive for plantation of 100,000 more mangroves in partnership with Pakistan Coast Guards. The event was attended by the Chief Guest Naeem Mughal, Director General, Sindh […]
BQPS-III First Turbine Commissioning On Fast Track
Karachi, April 8, 2021: K-Electric’s flagship 900 MW power plant, BQPS-III is progressing on fast track basis. Entire power train of first Unit consist of Gas Turbine, Steam Turbine , Generator and Heat Recovery Boiler have arrived and installed at the power utility’s Bin Qasim Power Complex. All relevant civil structural works is completed and […]